Task Management Software
 


PDF  Task Management Guide
 
 
 
 
New Articles New Articles RSS feed subscribe
 
What is a Management Dashboard?
The term Management Dashboard defines a wide range of data reporting and visualization tools or dashboards that allow using various performance & efficiency measures to report on an enterprise’s ability to organize and coordinate its activities in accordance with certain policies and in achievement of pre-determined objectives. What is a Management Dashboard?
 
 
 
 
New Checklists News RSS feed subscribe
 
Money Management Action Plan

In this Money Management Action Plan you can read a range of tips and suggestions that will help you manage your money in an effective manner.

Money Management Action Plan
 
 
 
Home » Solutions » Task Management Solution » Task Duration Solution
Task Duration Solution  

Task Duration Solution



 
 

Task duration management is a practice embedded into the Project Management, because it is necessary for a project manager to accurately estimate and pre-plan durations of all tasks included into the project, as they make up the overall project’s timeframe. Prior to delivering a project timeline, you need to carry out task duration estimation that includes certain amount of objective inputs, scientific forecasting, along with a significant portion of subjective judgment. Specifically, duration calculation process is based on the following inputs:

  • Expert Judgment – skillful estimators contribute their expertise and opinions to assist the project manager in planning durations of tasks;
  • Industrial Norms – durations of certain tasks are predefined by appropriate industrial standards or regulations, which are guaranteed by established quality-driven processes;
  • Risks Assessment – durations of some tasks can be seriously affected by external factors, so if the risks seem high enough it can be helpful to prolong influenced tasks to complete them via a risk-mitigated way;
  • Availability of resources – every working unit has certain capacity to process workloads, so it is necessary to not overload the resources with excessive assignments (such as competitive tasks);
  • Previous experience – available historical data to support estimation and planning;

How to estimate task duration?

There is one simple method based on three inputs: an optimistic estimate of duration (when all concerned factors aid the work maximally auspiciously), a pessimistic estimate (when work goes on a wrong track), and a most likely estimate (the most sober estimate based on probability of negative and positive scenarios). To get a more true representation of task duration you can use the following formula:

(Optimistic estimate) + (Pessimistic estimate) + (Most likely estimate)

3

This means to get an average from these three estimates. Let’s say you have 14 days for optimistic scenario, 30 days for pessimistic and 19 days for a most likely one. You need to sum them (63 days) and divide by 3 = 21 days. In other words you get 21 days for the most probable (average) duration.

Resource allocation is a process that usually directly affects duration of project tasks, because some activities will take much less time once more resources are assigned to them (because the amount of work will be processed in parallel by smaller portions). Business resources include the following matters:

  • Equipment;
  • Manpower;
  • Vehicles;
  • Premises;
  • Facilities;

Task Duration in Project Plan:

Sometimes, the project managers have to establish certain variance on the project to take into account related risks and some unforeseen circumstances that may hamper a project work. Duration variance may refer to the following factors:

  • Task Delay Allowance: certain lag is pre-scheduled to support probability of procrastination if  connected risks appear high enough, or for re-doing the job if something is failed;
  • Task Effort-driven Duration: when more working resources, than it was initially planned, are assigned to the task, its duration shortens;
Task Duration Solution

When a manager creates a timeline for the project, he needs to consider dependencies as far as many tasks on the project are directly connected, so if one task gets delayed, the following task becomes automatically delayed as well (and probably this will also affect the project’s finish date). That’s why it is necessary for a project manager to create and maintain a visually convenient duration chart with realistic estimates, where the project’s Critical Path is clearly determined, including all predecessors and successors, so it will be clear for the project manager to understand and forecast possible consequences if delaying some critical or secondary tasks.

VIP Task Manager is a program that can be used in the project team to plan (estimate) and track task durations, as well as to share and assign tasks to team members. This client-server tool features three modes to work with task durations: Task Tree (to decompose a project into smaller tasks), Task List (to view tasks in a more specified manner) and Calendar (to display tasks on a time-grid).

 

     

All Travel Checklists

new CentriQS -15% OFF
Business management software
for small & midsize enterprises

Play Demo

VIP Task Manager
Task management software
for teams & small offices
Play Demo / Download

 
 
 
home contact site map my account

 


Copyright © 2004 - 2024 VIP Quality Software, Ltd. All Rights Reserved.